Plan prévisionnel Détails Plan prévisionnel
|
|
Reserved for small businesses : |
No |
Year : |
2023 |
Public purchaser area : |
Ministry of Youth and Sports |
object : |
the synthetic turf of the football field at the Borj Cedria sports complex |
Period of realization : |
180 يوم |
Contracting procedure : |
Competitive bidding |
Proceedings : |
Normale |
Funding method : |
Budget |
Date of preparation of brochures conditions : |
2023/07/05 |
Publication date of the notice : |
2023/07/20 |
The date of the announcement of the competition : |
2023/08/21 |
Date of referral to the procurements committee : |
2023/10/05 |
Date response Procurement Commission : |
2023/10/26 |
Date publication of results : |
2023/10/30 |
Date notification des marchés |
2023/11/09 |
Start date for performance |
2023/11/23 |
|
|
|
|
|