![](../images/puce3.gif) Plan prévisionnel ![](../images/puce3.gif) Détails Plan prévisionnel
|
|
Reserved for small businesses : |
No |
Year : |
2024 |
Public purchaser area : |
Société Tunisienne d’Electricité et de Gaz |
object : |
Travaux de remplacement pylône N° 4-5-66-67 et tête du pylône N° 6 de la ligne 150KV Mdhila - Tozeur suite incident |
Period of realization : |
8mois |
Contracting procedure : |
International Competitive bidding |
Proceedings : |
Normale |
Funding method : |
Self financing |
Date of preparation of brochures conditions : |
2024/06/05 |
Publication date of the notice : |
2024/08/01 |
The date of the announcement of the competition : |
2024/09/04 |
Date of referral to the procurements committee : |
2024/10/02 |
Date response Procurement Commission : |
2024/12/05 |
Date publication of results : |
2025/01/02 |
Date notification des marchés |
2025/01/24 |
Start date for performance |
2025/01/31 |
|
|
|
|
|